  • Reclamation of the former Felindre Tinplate Works. The completed site contains some 300 acres of land for industrial development.

  • The contract involved demolition of structures above and below ground and the removal of waste and the reclamation of a former land fill site.

  • Site investigation with the excavation and sampling of more than 800 trail pits and 30 boreholes.

  • Bio-remediation of the contaminated material and the stockpiling of hydro–carbon contaminated material.

  • The contaminated material was excavated in a number of stages and deposited in a temporary stockpile and then screened to accelerate the bio-remediation process.

  • To achieve the design plateau levels, within the site some 260,000 tonnes of fill material was imported.

  • The material was sourced from the site of the Margam steelworks and was completed over a two-month period at an average rate of 6,000 tonnes per day.

  • With the earthworks in progress, two attenuation ponds with HDPE lining and a combined area of about 6000m2 were constructed and landscaped and subsurface drainage installed.