_Client: ___Welsh Assembly Goverment
_Value:___ £6 Million
_Duration:_ 2006 - 2007

_ _Walters UK Ltd
  • The project was placed on a NEC 3 Option C contract, with Early Contractor Involvement in development of target cost.

  • Walters UK are strategic partner throughout the procurement and construction phases.

  • The project involves the construction and preparation of five plateaus for future development together with a further larger plateau area for the incorporation of OCD (Ortho Clinical Diagnosis) Development.

  • The scheme also included the following major elements:-

  • Construction of a new estate road and major highway improvement to
    Felindre Road and Pantruthin lane.

  • Food compensation works adjacent to the Ewenni Fach River.

  • Provision of foul, surface water and highway drainage, including attenuation ponds.

  • Extensive ecology, environmental and landscaping considerations and solutions.

  • Provision on gas, water, electric and telecommunications.

[Close Window]

 

Walters UK Ltd - data sheet

Pencoed Technology Park - Walters UK Ltd

Pencoed Technology Park - Walters UK Ltd

Pencoed Technology Park - Walters UK Ltd

Pencoed Technology Park - Walters UK Ltd